Progress Report 08.13.10

Continued progress...
Joliet - Upon arrival of the rail train from Maryland crews quickly went to work.  All industrial trackage at Joliet is complete along with the main and siding.  The CB&Q local served as a test train switching all the industrial trackage.  All have passed inspection.  Joliet is my favorite place to hang out on the local so far.  Awesome switching opportunities there.

Rock Island - Industrial track has been cut and temporarily in place.  A local has worked the industrial trackage.  All have passed preliminary testing.  The track will be permanently affixed later this weekend.

Our company photographer was in the area today providing the photos below:
CB&Q Crossing
(CB&Q Left / Rock Island Right)
Joliet, Illinois






CB&Q Crossing
Joliet, Illinois







American Service Company
Coal Unloading Track
Joliet, Illinois






Joliet, Illinois
American Can Company (White Paper)
  w/ receiving in rear, load tracks in front

American Service Co.
Coal bridge (background)



Joliet, Illinois
Another view of the industrial trackage







Joliet, Illinois
Midwest Paper Stock Co. (Left)







Joliet, Illinois
American Service Company
Coal unloading track






Joliet, Illinois
Industrial Trackage
Town Station (foreground)






Joliet, Illinois
View of CB&Q Crossing from East







Joliet, Illinois
CB&Q Crossing


Stockdale (upper level)
Joliet (lower level)







Rock Island, Illinois








Main road through Rock Island, Illinois








Rock Island, Illinois








Rock Island, Illinois
Produce Distributor

1 comment:

  1. Get 'er done!

    That's all looking great. I really like the crossing at Joliet, and all of the industrial trackage. Very cool.

    ReplyDelete