Tuesday, August 24, 2010

Progress Report 08.23.10

Progress continues as crews lay the groundwork for laying rail in Blue Island.  Cork for the main and siding were laid from the first diamond in West Blue Island to staging. The cork was laid out (not glued) for both staging in Burr Oak Yard (Chicago) and West Davenport.  Crews are expected to start laying track Tuesday evening.

Management has declared that all track for Phase I will be complete by the end of Labor Day weekend.  Crews must push forward to keep this ambitious goal!

No comments:

Post a Comment