Clerk Report:
Waybill data entry was completed. All waybills were printed, but need to be cut.
Signal Maintainer Report:
Code line was connected in Rock Island. The welding tool played out so progress came to a screeching halt. Crews continued efforts by pulling the rough wiring for West Davenport, Davenport Yard, Joliet, Blue Island and Burr Oak Yard.
Car Department Report:
Another batch of cars have been brought down to the shop for inspection, upgrades and repairs. The Car Dept expects to have another 20 cars or so complete by the end of the weekend.