Sunday, January 15, 2012

Progress Report 01.15.12

Completed laying the track between the new crossover and the curved turnout at JD Tower.  Installed the long spur at the Proctor & Gamble plant.

Installed the new reversed crossover at Blue Island completing the trackwork for this massive project.

Hopefully, I can clean up the mess this week, clean the track and run some test trains through the area.  I will still have to go back and install slide switches for all the new turnouts.