Progress Report 03.01.13 - Clerical Work + Carrie Ave Shops

This morning, I worked on placing all the new car cards back where they belong.  That took some time, but not too bad.

The car shop replaced a handful of trucks/couplers on freight cars this morning.  They also replaced couplers on 13 locomotives.

This evening, The shop continued work on the truck/coupler renovation project replacing a total of twenty sets today.