CRI&P Goals (before Nov 20th, 2010):
- Design Blue Island track configuration (Complete)
- Purchase and complete all track installation for Phase I (Complete)
- Drop and solder all feeder wires (45% complete)
- Purchase and install all tortoise switch machines
(Changed - will utilize SPDT slide switches - Not purchased yet) - Industrial Trackage will need slide switches installed, but this can wait (see above)
- Paint and install blue backdrop for entire layout (put on hold)
- Purchase and install all decoders for remaining locomotives
(purchased - Peconic Shops to receive 9/14) - Install low profile wheel sets, cut all trip pins on all cars (98% complete - 4 remaining)
- Purchase/install DCC plug-in jacks (not purchased yet)
- Purchase/borrow additional throttle (negotiating lease terms with DB&W)
- Install, paint fascia. (put on hold)
- Install waybill boxes (will be temporarily installed, but not permanent until fascia is installed)
- Create waybills (90% complete)
- Stage Layout (not started yet)
Inaugural Operating Session ~ Saturday, Nov 20th, 2010
Day 224 of N Scale
173 Days since first board was cut (just under 6 months)
No comments: