Progress continues on the CRI&P.
Back Shop Report:
Carrie Ave Shops report that 15 locomotives are ready for service (decoder, trip pins cut, etc). Three are traveling to Peconic Shops for electronic upgrade this weekend. For the initial operating session, only 18 CRI&P locomotives will be active. Five locomotives will be leased from the Peconic Railroad.
Clerk Report:
All locomotive cards have been created.
Little by little, crews continue to make progress on the layout.
No comments:
Post a Comment