Signal Maintainer Report:
Got my soldering groove on. Utilized the CR&E's tip of keeping the booster on to instantly know of any shorts. Re-pulled the bus wire for the top level peninsula. I still have yet to pull the bus wire for the remainder of the top level, but holes are drilled. Signal Maintainer Little reports that the following are complete:
- West Davenport
- Davenport Yard
- Rock Island
- Joliet Grain Co.
- Blue Island
- Burr Oak Yard
Once wiring has been complete, a train will conduct extensive tests on the trackwork to determine any dead spots on the layout.