Tuesday, January 8, 2013

Progress Report 01.08.13 - New Grain Elevator

This evening, crews made quick work of filling in the bay at Moline.  The grain elevator was placed in it's final position and track laid.  Crews will need to return to sand the plaster, paint the roadway, install the slide switch and add new fascia.

It appears previous estimates of 9 spots was incorrect.  After the track had been laid, engineers spotted a total of 8 cars in the facility.  It's still a big improvement over the original 2 car spots.

Management is debating on names for the grain elevator.  It appears Continental Grain will be moving out.  The new tenant has yet to be determined.

Photos of the progress:





No comments: